Client - Esso Petroleum Company Ltd

FCCU Olefins Project & Turnaround

Off-site fabrication included steelwork, pipework and associated supports. The on-site pre turnaround work included the installation of 140 ton steelwork, new exchangers, fin fans, pumps and filters into a live unit. The project scope concluded with 600 tie-ins during a 7 week turnaround.

Subcontractors Managed

Scaffolding, Painting, Insulation, Craneage,
NDT, E&I, Vessel Cleaning, Standby’s,
Refractory, Machining.
Peak Labour 323